H₂ PCI projects

H2ercules Network
South-East

Last updated: 30 September 2026

Provided information is based on the Hydrogen Core Network as approved on 22 October 2024 by the Federal Network Agency (Bundesnetzagentur). However, they are subject to review within the Network Development Plan (NDP) process.

Karte des Leitungsabschnitts

Schematic representation of the pathway

The H2ercules Network South-East connects the German hydrogen core network in Bavaria with the hydrogen infrastructure planned in the Czech Republic. Through this connection, hydrogen from Eastern Europe and the Baltic Sea region — and, potentially, from additional import corridors — can be transported to major consumption centers in Bavaria and other regions of Germany.

The project includes the Rothenstadt–Waidhaus and Rothenstadt–Forchheim pipeline sections. The natural gas pipeline from Rothenstadt to Waidhaus (approximately 29 km), which will be converted for hydrogen transport, connects to the planned hydrogen network in the Czech Republic. The newly constructed Rothenstadt–Forchheim section, which is with approximately 102 km significantly longer, provides the link to Bavaria’s consumption centers. Both pipeline sections, with approximately 131 km in total, are scheduled to go into operation in 2032. Project partner in addition to OGE is NaTran Deutschland. OGE and NaTran Deutschland are both shareholders of MEGAL.

Fact sheet

approx. 131 km

Length

Rothenstadt — Waidhaus, Rothenstadt — Forchheim

Route

2032

Comissioning

up to 144 GWh/d from CZ to DE

Cross-border transmission capacity

planned

Status

Open Grid Europe GmbH, NaTran Deutschland GmbH, Mittel-Europäische-Gasleitungs­gesellschaft mbH & Co. KG (MEGAL)

Pipeline operator